| factor | weight | ranking |
| C21 Comply with the risk management policies and procedures | 0.1101 | 1 |
| C15 Determine the risk response responsible individual | 0.1029 | 2 |
| C8 Risk triggering condition | 0.0893 | 3 |
| C18 Identify new risk | 0.0866 | 4 |
| C16 Negative risk response | 0.069 | 5 |
| C19 Existing risk reevaluate | 0.0581 | 6 |
| C1 Support of Stakeholders | 0.0482 | 7 |
| C10 Risk priority ranking | 0.0462 | 8 |
| C17 Positive risk response | 0.0462 | 9 |
| C22 Adjust cost/schedule contingency reserve | 0.0422 | 10 |
| C7 Risk identification method and technology | 0.0401 | 11 |
| C11 Risk urgency evaluation | 0.031 | 12 |
| C12 Quantification risk priority list | 0.031 | 13 |
| C20 Cancel outdated risk | 0.0283 | 14 |
| C3 Establish risk contingency reserve using method | 0.0275 | 15 |
| C6 Risk description format | 0.0269 | 16 |
| C5 Risk classification | 0.0254 | 17 |
| C9 Risk attitude of the group and the other stakeholders | 0.0208 | 18 |
| C13 Probability to fulfill the project objective | 0.0208 | 19 |
| C4 Define the risk probability and influence | 0.0192 | 20 |
| C2 Cost and schedule activities | 0.0164 | 21 |
| C14 Quantitative analysis method | 0.0139 | 22 |