Control the risk consistency ratio of the judgment matrix: 0.0057; the weight to the target: 0.3253; λmax: 5.0256 | ||||||
Control the risk | C18 Identify new risk | C19 Existing risk reevaluate | C20 Cancel outdated risk | C21 Comply with the risk management policies and procedures | C22 Adjust cost/schedule contingency reserve | Wi |
C18 Identify new risk | 1 | 1.4918 | 3.3201 | 0.6703 | 2.2255 | 0.2663 |
C19 Existing risk reevaluate | 0.6703 | 1 | 2.2255 | 0.4493 | 1.4918 | 0.1785 |
C20 Cancel outdated risk | 0.3012 | 0.4493 | 1 | 0.3012 | 0.6703 | 0.0869 |
C21 Comply with the risk management policies and procedures | 1.4918 | 2.2255 | 3.3201 | 1 | 2.2255 | 0.3386 |
C22 Adjust cost/schedule contingency reserve | 0.4493 | 0.6703 | 1.4918 | 0.4493 | 1 | 0.1296 |