Benefits | Descriptive | One-sample t-test | Remark | ||||
Mean | Std. Dev. | t | Mean Diff. | Sig. (2-tailed) | |||
Facilitate the achievement of project success and the objectives within the scheduled time | 3.81 | 1.303 | −1.391 | −0.193 | 0.168 | Agree | |
Reduce all the associated project risk during the bidding and the construction processes | 2.49 | 1.135 | −12.496 | −1.511 | 0.00 | Disagree | |
Maximize overall value to the project owner or client | 3.24 | 1.304 | −5.476 | −0.761 | 0.00 | Neutral | |
Enable the client or project owner to select contractors who are performers for the project | 4.43 | 0.498 | 8.131 | 0.432 | 0.00 | Agree | |
Minimize the possibility of contractor default | 3.94 | 1.207 | −0.442 | −0.057 | 0.66 | Agree | |
Save the project owner a lot of time | 4.00 | 0.773 | 0.00 | 0.00 | 1.00 | Agree |