Row | Hindrance Factors Impeding the Application of VM | Relative weight |
1 | Lack of culture and incentive for thrift and good use of resources | 23% |
2 | Lack of support and active participation from owners and stakeholders | 18% |
3 | Lack of legislation providing for application of VE in the construction industry | 16% |
4 | Lack of knowledge about VE | 8% |
5 | Lack of risk and innovation | 8% |
6 | Lack of workshops | 7% |
7 | Lack of time to conduct VE studies | 6% |
8 | Lack of VE experts | 5% |
9 | Conformity with contractor’s opinion | 4% |
10 | Lack of cooperation and interaction with the internal VE team | 4% |