| N˚ | Component of the MHPP | Total Price (FCFA) |
| 1 | Civil engineering works: Total 1 = T1 | 43,125,062 |
| 2 | Metal construction: Total 2 = T2 | 1,700,000 |
| 3 | Turbo-generator group: Total 3 = T3 | 18,775,000 |
| 4 | Equipment for transmission and supply of electricity: Total 4 = T4 | 9,800,000 |
| Others cost (administration and legal fees): Total 5 = T5 | 7,000,000 | |
| Total = T1 + T2 + T3 + T4 + T5 | 80,400,062 | |
| Contingences 10% = I | 8,040,006 | |
| Grand Total | 88,440,068 | |