S No

Activity

Duration

Remarks

1.

Identification of Project areas, budgeting and project write-up

11th June-30th August 2002

(7 weeks)

Carried out by MLHHSD

2.

Aerial Photographs to record developments on identified areas

22nd-23rd August 2002

2 days

It is assumed there were no clouds on these two days

3.

Preparation of detailed land use plans

1st July 2002-31st December 2002

(6 months) (24 weeks)

Carried out by MLHHSD. Started before land was acquired

4.

Public awareness campaigns

27th August-21st September

(3½ weeks)

Time allocated considered inadequate

5.

Acquisition of land by the President

31st October 2002

Notice for land acquisition was

published on 5 November 2002 (GN 899)

6.

Valuation for determining compensation

started 1st October 2002

Valuation started before land was legally acquired.

7.

Land surveying

Started 12th December 2002

8.

Engineering works for roads

Started 21st January 2003

Excluded drains and water and electricity infrastructure to reduce costs.

9.

Plot allocation

Started 13th March 2003