S No | Activity | Duration | Remarks |
1. | Identification of Project areas, budgeting and project write-up | 11th June-30th August 2002 (7 weeks) | Carried out by MLHHSD |
2. | Aerial Photographs to record developments on identified areas | 22nd-23rd August 2002 2 days | It is assumed there were no clouds on these two days |
3. | Preparation of detailed land use plans | 1st July 2002-31st December 2002 (6 months) (24 weeks) | Carried out by MLHHSD. Started before land was acquired |
4. | Public awareness campaigns | 27th August-21st September (3½ weeks) | Time allocated considered inadequate |
5. | Acquisition of land by the President | 31st October 2002 | Notice for land acquisition was published on 5 November 2002 (GN 899) |
6. | Valuation for determining compensation | started 1st October 2002 | Valuation started before land was legally acquired. |
7. | Land surveying | Started 12th December 2002 |
|
8. | Engineering works for roads | Started 21st January 2003 | Excluded drains and water and electricity infrastructure to reduce costs. |
9. | Plot allocation | Started 13th March 2003 |
|