Power plant | PV system | CSP tower | Wind turbine | NGCC | ISCC |
Annual energy production | 17,697,652 kWh | 38,036,716 kWh | 40,100,984 kWh | 63,571,565 kWh | 64,943,646 kWh |
Net capital cost | $10,351,020 | $86,346,059 | $74,000,00 | $10,830,000 | $17,340,562 |
Capacity factor | 20.2% | 43.9% | 45.8% | 72.75% | 74.31% |
LCOE | 2.63 cents/kWh | 19.6 cents/kWh | 5.98 cents/kWh | 9.91 cents/kWh | 18.9 cents/kWh |
Annual O&M cost | $122,956 | $1,074,642 | $505,354 | $4,420,152 | $4,835,160 |
Land requirement | 36.3 acres | 241 acres | 15 acres | 3.43 acres | 13.5 acers |