5 May 2015

Foreign passages of the Great Belt

S&B (2015)

1 June 2015

EQA of ferry services started

KPMG (2016)

29 June 2015

EU appropriates reduced subsidy

Børsen (2015)

1 October 2015

“Due diligence” of reserves etc.

TRM (2015a)

2 October 2015

Financial uncertainty analysis

Bredsdorff (2015a)

21 October 2015

EQA of tunnel commissioned

Ernst & Young (2016)

10 November 2015

EQA of road traffic forecasts published

COWI (2015b)

11 November 2015

Appl. of New Construction Budgeting

TRM (2015b)

12 November 2015

Traffic forecast approved by Minister

TRM (2015c)

12 November 2015

EQA of road traffic transfer requested

TRM (2015d)

20 November 2015

Traffic transfer from the Great Belt

Bredsdorff (2015b)

26 November 2015

Minister ignores criticism from EQA

Schjær-Jacobsen (2015b)

13 January 2016

Financial high risk project

Schjær-Jacobsen (2016a)

20 January 2016

Proposal of Great Belt traffic analysis

S&B (2016)

24 January 2016

EQA of competition by ferry services published

KPMG (2016)

28 January 2016

EQA of tunnel published

Ernst & Young (2016)

January 2016

Competition between ferry and tunnel

Aigner (2016)

3 February 2016

Financial analysis

Femern A/S (2016a)

10 February 2016

Memo: Financial analyses

Femern A/S (2016b)

22 February 2016

High risk business case

Schjær-Jacobsen (2016b)

4 March 2016

Binding political agreement

Danish Parliament (2016)

4 March 2016

Upgrading of existing rail track begins

TRM (2016a)

4 March 2016

Upgrading of existing rail track begins

Ingeniøren (2016a)

4 March 2016

COWI is the big winner

Ingeniøren (2016b)

10 - 18 March 2016

Correspondence Scandlines-Ministry

TRM (2016b)