Plant capacity

Net annual electricity production

2200.00 kW

8017.2 MWh/year

Cost of equipment

Power generation equipment

· 2 ORC Units of 1.1 MW

· Boiler

· Furnace

· Convoyer belt

· Flue gas cleaning system

· Storage

· Moisture and fire control system

· Ash extraction system

3,700,000$

1,716,561$

1,595,210$

352,320$

1,000,000$

500,000$

150,000$

200,000$

Feasibility study

100,000$

Development

3,500,000$

Engineering

200,000$

Civil engineering works

1,750,130$

Fuel cost

· Biomass price

· Annual consumption

· Total cost

55 $/t

39,575 t

2,176,603$

Total costs of the CHP plant

13,491,084$

Heating network

· Main mine hoses

· Secondary line pipes

· Energy transfer stations

Total heating network costs

5,792,738$

7,160,440$

1,988,436$

14,941,614$

Total investment costs

28,432,698$