Plant capacity Net annual electricity production | 2200.00 kW 8017.2 MWh/year |
Cost of equipment |
|
Power generation equipment · 2 ORC Units of 1.1 MW · Boiler · Furnace · Convoyer belt · Flue gas cleaning system · Storage · Moisture and fire control system · Ash extraction system |
3,700,000$ 1,716,561$ 1,595,210$ 352,320$ 1,000,000$ 500,000$ 150,000$ 200,000$ |
Feasibility study | 100,000$ |
Development | 3,500,000$ |
Engineering | 200,000$ |
Civil engineering works | 1,750,130$ |
Fuel cost · Biomass price · Annual consumption · Total cost |
55 $/t 39,575 t 2,176,603$ |
Total costs of the CHP plant | 13,491,084$ |
Heating network · Main mine hoses · Secondary line pipes · Energy transfer stations Total heating network costs |
5,792,738$ 7,160,440$ 1,988,436$ 14,941,614$ |
Total investment costs | 28,432,698$ |