Cycle 1

Objective

Result

1. July 2022

Gather historical data, information from the VKK website, minutes of meetings.

Historic information to create the context.

2. August 2022

Information on activities and events. First six interviews. The themes from theoretical model 1 [48] are defined for coding.

Timeline 2007-2022

Audio recordings of interviews. Questionnaire.

Cycle 2

3. September- October 2022

Eleven successive interviews with participants. Reflection on the results creates the need to add a theoretical model 2 [49] .

Recordings, transcripts, translations and coding in Excel.

Cycle 3

4. October- November 2022

Final interviews.

Questionnaire sent out to fourteen aldermen of local Community Councils.

Recording, transcripts, translations, and coding in Excel.