Hypo | Relation | Std. Beta | Std. Error | t-value | P Values | Decision |
H1 | Organizational Factor -> TAM Project Success | 0.083 | 0.044 | 1.816 | 0.069 | Not Supported |
H2 | Human Resource Factor -> TAM Project Success | 0.101 | 0.038 | 2.507 | 0.012 | Supported |
H3 | Project Management Factor -> TAM Project Success | 0.220 | 0.050 | 4.386 | 0.000 | Supported |
H4 | Project Factors -> TAM Project Success | 0.217 | 0.074 | 2.788 | 0.005 | Supported |
H5 | Economic Resilience -> TAM Project Success | 0.057 | 0.051 | 1.142 | 0.254 | Not Supported |
H6 | Personality Traits -> TAM Project Success | 0.124 | 0.056 | 2.320 | 0.020 | Supported |