EVM elements

Explanatory

Planned Value

(PV)

Cumulative maintenance effort as planned value

up to operational time t

Earned Value

(EV)

Cumulative maintenance effort up to operational

time t viewed on the same scale as BAC

Actual Cost

(AC)

Cumulative maintenance effort up to operational

time t in actual

Budget at Completion

(BAC)

Total budget at the end of open source project

Cost Variance

(CV)

E [ C V * ( t ) ] obtained from EV-AC

Cost Performance Index

(CPI)

E [ C P I * ( t ) ] obtained from EV/AC

Schedure Variance

(SV)

SV obtained from EV-PV

Schedule Performance Index

(SPI)

SPI obtained from EV/PV

Estimate at Completion

(EAC)

E [ E A C * ( t ) ] obtained from BAC/CPI

Estimate to Complete

(ETC)

E [ E T C * ( t ) ] obtained from (BAC − EV)/CPI