| EVM elements | Explanatory |
| Planned Value (PV) | Cumulative maintenance effort as planned value up to operational time t |
| Earned Value (EV) | Cumulative maintenance effort up to operational time t viewed on the same scale as BAC |
| Actual Cost (AC) | Cumulative maintenance effort up to operational time t in actual |
| Budget at Completion (BAC) | Total budget at the end of open source project |
| Cost Variance (CV) | obtained from EV-AC |
| Cost Performance Index (CPI) | obtained from EV/AC |
| Schedure Variance (SV) | SV obtained from EV-PV |
| Schedule Performance Index (SPI) | SPI obtained from EV/PV |
| Estimate at Completion (EAC) | obtained from BAC/CPI |
| Estimate to Complete (ETC) | obtained from (BAC − EV)/CPI |