EVM Elements | Explanation |
Planned Value (PV) | total budget estimated at the planning phase up to a certain point |
Earned Value (EV) | total budgeted cost resources of processes completed at a certain point |
Actual Cost (AC) | total actual cost resources invested |
Budget at Completion (BAC) | total budget to completion defined at the time of planning |
Cost Variance (CV) | shows whether a project is under or over budget CV = EV − AC |
Cost Performance Index (CPI) | evaluates how efficiently the project is using its resources. CPI = EV/AC |
Schedure Variance (SV) | determines whether a project is ahead of or behind schedule. SV = EV − PV |
Schedule Performance Index (SPI) | evaluates how efficiently the project team is using its time. SPI = EV/PV |
Estimate at Completion (EAC) | final cost of the project in case of continuing current performance trend. EAC = BAC/CPI |
Estimate to Complete (ETC) | shows what the remaining work will cost. ETC = (BAC − EV)/CPI |