BBPCUDB-3371574-073/74-019 (bridge1st) | Babai River Bridge, Salyan | 2074-03-09 | 36 months from contract agreement | 5% work progress |
BBPCUDB-3371574-073/74-019 (bridge2nd) | Babai River Bridge, Salyan | 5% work progress | ||
BBPCUDB-3371574-073/74-021 | Doda River Bridge, Kanchanpur | 2074-07-22 | 36 months from contract agreement | 60% work progress |
BBPCUDB-3371574-073/74-026 | Kandra River Bridge, Bijuliya | 2074-03-11 | 30 months from contract agreement | 50% work progress |
BBPCUDB-3371574-073/74-034 (Bridge 2nd) | Gwar River Bridge, Dang | 2074-03-11 | 36 months from contract agreement | 99% work progress |
BP-DB-070/71-01 | Design & Build of Bheri Rimna & Jugai Khola Bridge along Chinchu Jajarkot Road | 2/27/2071 | 36 months from Signing Contract | 2074-06-11 |
BP-DB-068/69-05 | Design & Build of Bheri Bridge on Surkhet-Purandhara Road in Surkhet District | 3/20/2069 | 48 months from Signing Contract-ACC, 60 months from signing contract-SCC | 2076-05-05 |
PCU-DB-WR-071/72-20 | Design & Build of Bridge (Goji khola and Chedegad Bridge) Chhinchu-Jajarkot Road | 3/24/2072 | 48 months from Signing Contract | 2076-03-24 |
PCU-DB-WR-071/72-26 | D& B of Bheri bridge, Jamughat Tatapani-9 to Babiyachaur, Surkhet | 3/30/2072 | 48 months from Signing Contract | 2075-05-18 |
PCU-DB-WR-071/72-33 | Design & Build of Karnali Bridge, Kachalighat, Kuhine, Surkhet | 3/28/2072 | 48 months from Signing Contract | 40% work progress |
BBPCUDB-3373204-073/74-002 (Bridge 1st) | Man River Bridge, Gulariya | 2074-08-22 | 36 months from contract agreement | 15% work progress |
BBPCUDB-3373204-073/74-002 (Bridge 2nd) | Bhada River Bridge, Gulariya | 30% work progress | ||
BBPCUDB-3373204-073/74-034 (Bridge 1st) | Guhar River Bridge Dang | 2074-03-11 | 36 months from contract agreement | 90% work progress |