Contract No: | Name of Project: | Agreement Date | Intended Completion Period | Completion Date/progress |
BP-DB-070/71-02 | Design & Build of Bheri Bridge along Ghumi-Patihalna-Chowr Road, Mahelkuna | 2/30/2071 | 36 months from Contract Agreement | 2074-02-29 |
BP-DB-068/69-06 | Design & Build of Babai bridge, at Lathuwaghat-in Bardiya District | 3/20/2069 | 2075-06-11 | 2075-06-11 |
PCU-DB-WR-071/72-19 | Design and Build of Babai Nadi Bridge Matera Bhojpur, Dang | 3/25/2072 | 36 months from Contract Agreement | 2076-04-10 |
PCU-DB-WR-071/72-27 | Design and Build of Gowar khola Bridge, Pukar pasal (Tarigaun VDC) to Lauhara (Manpur VDC), Dang | 3/30/2072 | 36 months from Contract Agreement | 2074-03-29 |
PCU-DB-WR-071/72-32 | Design and Build of Patukhola Bridge, Sukaura, Tulsipur MP to Hekuli VDC-9 Sukadewa Dang | 3/29/2072 | 36 months from Contract Agreement | 2075-06-28 |
BBPCU-DB-3371574-072/73-20 | Design & Build of Daduwa Khola Bridge, Dhadwar, Bardiya | 3/29/2073 | 34 months from Contract Agreement | 2075-06-28 |
BBPCU-DB-3371574-072/73-22 | Design and Build of Two Bridges 1. Rapti Bridge Connecting Sisniya VDC-2 & Gobadiya VDC-6, Mahadeva, Dang & 2. Rapti Bridge, Jahare Connecting Satbariya VDC and Rajapur | 3/28/2073 | 48 months from Contract Agreement | 90% progress |
BBPCU-DB-3371574-072/73-23 | Design and Build of Bridge of Two Bridges 1) Babai Nadi Bridge, Connecting Loha Dabara and Dawangpur, Dang & 2) Babai Nadi Bridge, Goltakuri ko Baki ra Hekuli VDC ko Baibang bich ma | 3/30/2073 | 33 months from Contract Agreement | 70% work progress |
BBPCU-DB-3371574-072/73-37 | Design and Build of Rapti Khola Bridge, Hasnapur chowk, Satbariya-1 & Chappa, Bela-5, Dang | 3/30/2073 | 36 months from Contract Agreement | 35% work progress |
BBPCU-DB-3371574-072/73-38 | Design and Build of Babai River Bridge, Matheura-6 and Dholpur-8, Panchakule VDC, Dang | 3/30/2073 | 30 months from Contract Agreement | 30% work progress |
BBPCUDB3371574-073/74-003 | Bheri river bridge, Jajarkot | 2074-03-09 | 30 months from contract agreement | contract termination due to disaster |
BBPCUDB3371574-073/74-004 | Bheri river bridge, Surkhet | 2074-08-27 | 30 months from contract agreement | 15% work progress |
BBPCUDB-3371574-073/74-008 | Rapti river bridge, Satbariya | 2074-08-26 | 48 months from contract agreement | 30% work progress |
BBPCUDB-3371574-073/74-009 | Rapti river bridge, Machhebash-Dampur | 2074-08-27 | 42 months from contract agreement | 65% work progress |
BBPCUDB-3371574-073/74-013 | Karnali River Bridge, Ghatgau | 2074-08-27 | 48 months from contract agreement | 20% work progress |
BBPCUDB-3371574-073/74-015 | Bheri River Bridge, Ghusenigada Ghat | 2074-08-27 | 42 months from contract agreement | 75% work progress |
BBPCUDB-3371574-073/74-018 | Rapti River Bridge, Pyuthan | 2074-03-09 | 36 months from contract agreement | 25% work progress |