Contract No:

Name of Project:

Agreement Date

Intended Completion Period

Completion Date/progress

BP-DB-070/71-02

Design & Build of Bheri Bridge along Ghumi-Patihalna-Chowr Road, Mahelkuna

2/30/2071

36 months from Contract Agreement

2074-02-29

BP-DB-068/69-06

Design & Build of Babai bridge,

at Lathuwaghat-in Bardiya District

3/20/2069

2075-06-11

2075-06-11

PCU-DB-WR-071/72-19

Design and Build of Babai Nadi Bridge Matera Bhojpur, Dang

3/25/2072

36 months from

Contract Agreement

2076-04-10

PCU-DB-WR-071/72-27

Design and Build of Gowar khola Bridge, Pukar pasal (Tarigaun VDC) to Lauhara (Manpur VDC), Dang

3/30/2072

36 months from Contract Agreement

2074-03-29

PCU-DB-WR-071/72-32

Design and Build of Patukhola Bridge, Sukaura, Tulsipur MP to Hekuli VDC-9 Sukadewa Dang

3/29/2072

36 months from Contract Agreement

2075-06-28

BBPCU-DB-3371574-072/73-20

Design & Build of Daduwa Khola Bridge, Dhadwar, Bardiya

3/29/2073

34 months from

Contract Agreement

2075-06-28

BBPCU-DB-3371574-072/73-22

Design and Build of Two Bridges 1. Rapti Bridge Connecting Sisniya VDC-2 & Gobadiya VDC-6, Mahadeva, Dang & 2. Rapti Bridge, Jahare Connecting Satbariya VDC and Rajapur

3/28/2073

48 months from Contract Agreement

90% progress

BBPCU-DB-3371574-072/73-23

Design and Build of Bridge of Two Bridges 1) Babai Nadi Bridge, Connecting Loha Dabara and Dawangpur, Dang & 2) Babai Nadi Bridge, Goltakuri ko Baki ra Hekuli VDC ko Baibang bich ma

3/30/2073

33 months from Contract Agreement

70% work progress

BBPCU-DB-3371574-072/73-37

Design and Build of Rapti Khola Bridge, Hasnapur chowk, Satbariya-1 & Chappa, Bela-5, Dang

3/30/2073

36 months from Contract Agreement

35% work progress

BBPCU-DB-3371574-072/73-38

Design and Build of Babai River Bridge, Matheura-6 and Dholpur-8,

Panchakule VDC, Dang

3/30/2073

30 months from Contract Agreement

30% work progress

BBPCUDB3371574-073/74-003

Bheri river bridge, Jajarkot

2074-03-09

30 months from contract agreement

contract termination due to disaster

BBPCUDB3371574-073/74-004

Bheri river bridge, Surkhet

2074-08-27

30 months from contract agreement

15% work progress

BBPCUDB-3371574-073/74-008

Rapti river bridge, Satbariya

2074-08-26

48 months from contract agreement

30% work progress

BBPCUDB-3371574-073/74-009

Rapti river bridge, Machhebash-Dampur

2074-08-27

42 months from contract agreement

65% work progress

BBPCUDB-3371574-073/74-013

Karnali River Bridge, Ghatgau

2074-08-27

48 months from contract agreement

20% work progress

BBPCUDB-3371574-073/74-015

Bheri River Bridge, Ghusenigada Ghat

2074-08-27

42 months from contract agreement

75% work progress

BBPCUDB-3371574-073/74-018

Rapti River Bridge, Pyuthan

2074-03-09

36 months from

contract agreement

25% work progress