| Relationships | Pearson correlation coefficient (r) | p-value |
| Productivity vs Equipment downtime | −0.89 | <0.001 |
| Productivity vs Conveyor overloading delays | −0.72 | <0.001 |
| Productivity vs Bins overloading delays | −0.48 | 0.022 |
| Productivity vs Preventive maintenance delays | −0.39 | 0.039 |
| Productivity vs Gas management delays | −0.25 | 0.049 |