| Timeline | Community Water Education Outreach Implementation Plan |
| Week 3 | Draft, print and ship booklets for school children |
| Week 8 | Booklets are distributed to teachers at five training sessions |
| 18 months | Carabeyllo pipe completed, first farmer presentation |
| (1.5 years) | |
| 36 months | Chaclacayo and Ate pipe completed, second farmer presentation |
| (3 years) | |
| 54 months | Pachacama pipe completed, third farmer presentation |
| (4.5 years) |