Estimated Constructions | Estimated Constructions Data | |||||
EAC (INCC) | ADMC (INCC) | EXC (INCC) | Estimated (TCC) | Total Cost Incurred (INCC) | Error of the Estimation (%) | |
1 | 33.59206 | 4.50000 | 1.17500 | 39.26706 | 39.88254 | −1.57% |
2 | 100.51983 | 12.24000 | 24.19000 | 136.94983 | 137.78187 | −0.61% |
3 | 32.44961 | 4.32000 | 0.82000 | 37.58961 | 37.77413 | −0.49% |
4 | 49.46099 | 4.76000 | 1.35500 | 55.57599 | 55.24855 | 0.59% |
5 | 12.66566 | 1.68000 | 0.73500 | 15.08066 | 15.01165 | 0.46% |