Causes of Change Orders

Percentage of Respondents

Median

Mode

Strongly Disagree

Disagree

Neither Agree or Disagree

Agree

Strongly Agree

Severity Index

1

Changes initiated by clients

0.7

0.7

6.6

15.1

77.0

93.42

5.00

5

2

Design errors

1.3

1.3

0.6

33.5

63.2

91.23

5.00

5

3

Inconsistency between contract documents

0.6

0.6

3.9

47.7

47.1

88.00

4.00

4

4

Lack of communication between project parties

0

1.9

6.5

63.9

27.7

83.48

4.00

4

5

Incomplete design

0.6

1.9

27.1

59.4

11.0

75.61

4.00

4

6

Estimation errors

0.6

5.2

31.6

55.5

7.1

72.65

4.00

4

7

Time lag between design and construction phases

0

7.1

38.1

51.6

3.2

70.19

4.00

4

8

Different site conditions

0.6

16.9

55.2

26.0

1.3

62.08

3.00

3

9

Shortages of materials

13.0

43.5

36.4

7.1

0

47.53

2.00

2