Q

Progress Reports

Percentage of Acceptance

Public Owner

Private Owner

PM Firms

Eng. Firms

Contractor

2

A specific and effective monitoring system

12%

13%

100%

40%

30%

3

The benefits of periodic progress reports prepared by any of the contracting parties

64%

20%

87%

47%

33%

4

The benefits of progress reports in alerting against possible future claims

32%

27%

73%

33%

17%

5

The accuracy of the Percent completion in progress reports against the Actual percent

28%

20%

73%

40%

13%

6

The impact of progress reports on limiting problems and disputes

28%

20%

47%

13%

17%

7

Progress Report Effectiveness

64%

27 %

87%

47%

33%

The Percentage Average of each Contracting Parties Acceptance

38%

21%

78%

37%

24%

The Percentage Average of all Contracting Parties Acceptance (without the PM Firms who prepares the progress reports) is 40%