| Q | Progress Reports | Percentage of Acceptance | ||||
| Public Owner | Private Owner | PM Firms | Eng. Firms | Contractor | ||
| 2 | A specific and effective monitoring system | 12% | 13% | 100% | 40% | 30% |
| 3 | The benefits of periodic progress reports prepared by any of the contracting parties | 64% | 20% | 87% | 47% | 33% |
| 4 | The benefits of progress reports in alerting against possible future claims | 32% | 27% | 73% | 33% | 17% |
| 5 | The accuracy of the Percent completion in progress reports against the Actual percent | 28% | 20% | 73% | 40% | 13% |
| 6 | The impact of progress reports on limiting problems and disputes | 28% | 20% | 47% | 13% | 17% |
| 7 | Progress Report Effectiveness | 64% | 27 % | 87% | 47% | 33% |
| The Percentage Average of each Contracting Parties Acceptance | 38% | 21% | 78% | 37% | 24% | |
| The Percentage Average of all Contracting Parties Acceptance (without the PM Firms who prepares the progress reports) is 40% | ||||||