| Engaged in construction projects | Yes | No | Pearson Chi-Square | Cramer’s V | N of Valid Cases | Df | Asymp. Sig. (2-sided) |
Freq (%) | Freq (%) | |||||||
Years of Project Experience | 0 - 5 yrs | 14 (25.0) | 4 (100.0) | 10.000a | 0.408 | 60 | 3 | 0.0019 |
6 - 10 yrs | 27 (48.2) | 0 (0.0) |
|
|
|
|
| |
11 - 15 yrs | 7 (12.5) | 0 (0.0) |
|
|
|
|
| |
≥15 yrs | 8 (14.3) | 0 (0.0) |
|
|
|
|
| |
Years of Project Experience | Participation in project design phase | |||||||
0 - 5 yrs | 14 (25.0) | 4 (100.0) | 10.000a | 0.408 | 60 | 3 | 0.0019 | |
6 - 10 yrs | 27 (48.2) | 0 (0.0) |
|
|
|
|
| |
11 - 15 yrs | 7 (12.5) | 0 (0.0) |
|
|
|
|
| |
≥15 yrs | 8 (14.3) | 0 (0.0) |
|
|
|
|
| |
Frequency of risk assessment at design phase | Study of risk management or/and project management course | |||||||
Not frequent | 12 (22.2) | 4 (66.7) | 7.222a | 0.347 | 60 | 3 | 0.065 | |
Fairly frequent | 18 (33.3) | 0 (0.0) |
|
|
|
|
| |
Frequent | 14 (25.9) | 2 (33.3) |
|
|
|
|
| |
Very frequent | 10 (18.5) | 0 (0.0) |
|
|
|
|
| |
Evaluation of knowledge of risk management | Study of risk management or/and project management course | |||||||
Low | 2 (50.0) | 2 (50.0) | 8.227a | 0.370 | 60 | 2 | 0.016 | |
Average | 43 (91.5) | 4 (8.5) |
|
|
|
|
| |
High | 9 (100.0) | 0 (0.0) |
|
|
|
|
| |
Importance of risk management assessment in project design phase | Performed any risk assessment for project | |||||||
Not important | 3 (100.0) | 0 (0.0) | 1.800a | 0.173 | 60 | 2 | 0.407 | |
Fairly important | 9 (60.0) | 6 (40.0) |
|
|
|
|
| |
Very important | 28 (66.7) | 14 (33.3) |
|
|
|
|
|