Project

Location

Expected starting period

Actual starting period

Current status

Gap

Remarks

Construction of

1 no. 12 seater aqua privy

Kokofu

1/01/2013-31/12/2013

21/2/2013-21/06/2013

Completed

-

Successful implementation of projects

Construction of culvert and drains and rehabilitation of Mrs. Lamptey’s road (phase 2)

Bekwai

1/01/2013-31/12/2013

-

Not started

Project not implemented as planned by the assembly

Unfavorable weather condition impeded the first phase of the project and this affected the commencement of the second phase