Project | Location | Expected starting period | Actual starting period | Current status | Gap | Remarks |
Construction of 1 no. 12 seater aqua privy | Kokofu | 1/01/2013-31/12/2013 | 21/2/2013-21/06/2013 | Completed | - | Successful implementation of projects |
Construction of culvert and drains and rehabilitation of Mrs. Lamptey’s road (phase 2) | Bekwai | 1/01/2013-31/12/2013 | - | Not started | Project not implemented as planned by the assembly | Unfavorable weather condition impeded the first phase of the project and this affected the commencement of the second phase |