Scenario | Bottleneck | Production (FE per year) | Percentage raise regarding | ||
Process | Nr. | Previous scenario | Scenario 1 | ||
1 | Hot rolling | 28 | 28 | - | - |
2 | Four processes | 32 | 30 | 7 | 7 |
3 | FE assembly | 38 | 33 | 10 | 18 |
4 | UF4 drying | 9 | 34 | 3 | 21 |
5 | Stripping | 37 | 36 | 6 | 29 |
6 | Hot rolling | 28 | 38 | 6 | 36 |
7 | Four processes | 32 | 40 | 5 | 43 |
8 | Dimensional inspection | 35 | 42 | 5 | 50 |
9 | UF4 drying | 9 | 42 | 0 | 50 |
10 | Initial cut | 31 | 45 | 7 | 61 |