No. | Processes | Time (hours) |
23 | Reception of aluminum boards | 1.67 |
24 | Cladding and framing preparation | 3.28 |
25 | Cladding and framing stripping | 4.55 |
26 | Assembly of the set | 1.12 |
27 | Welding of the set | 1.50 |
28 | Hot rolling and annealing | 8.83 |
29 | Blister inspection | 0.54 |
30 | Cold rolling | 1.08 |
31 | Initial cut | 3.43 |
32 | Four processes on fuel plates (FP) | 8.37 |
33 | Final cut | 2.86 |
34 | Surface treatment | 2.21 |
35 | Dimensional inspection and second radiography of FP | 3.89 |
36 | Scratching test | 1.67 |
37 | Stripping of FP and FE components | 6.33 |
38 | FE assembly | 6.82 |
39 | Quality control | 3.37 |
40 | Nozzle fixation | 1.06 |
41 | Handling pin fixation | 0.86 |
42 | FE dimensional control | 0.96 |
43 | FE cleaning and packing | 1.12 |
44 | Delivery of the finished FE | 0.48 |
| TOTAL | 56.50 |