Results Chain Level | Effect | Indicator | Baseline (2004) | Target (2011) | Actual (2011) | Judgement |
Outputs | To rehabilitate the road between Arusha and Athi River | Km of road | 0 | 242 | 232 | Positive |
To reduce cost of cross-border transactions | N. of OSBP | 0 | 1 | 0 | Negative | |
To study the feasibility of other cross-border roads | N. of cross-border road design studies | 0 | 2 | 2 | Positive | |
To improve the technical capacity of the EAC | N. of new engineers in EAC’s rank | 0 | 2 | 0 | Very negative | |
To improve knowledge on contracting capacity in East Africa | N. of reports | 0 | 1 | 0 | Very negative | |
Outcomes | To increase traffic between Arusha and Athi River | Annual Average Daily Traffic (AADT) | - | +36% | +45%* | Positive |
To reduce travel time | Travel time (minutes) | 240 | 150 | 150 | Very Positive | |
To reduce cost of trip | Vehicles operating cost (USD per vehicle/km) | 0.56 | 0.45 | 0.42 | Very Positive | |
To increase road safety | N. of accidents | - | - | - | Uncertain | |
Development Impacts | To increase cross-border trade | Freight crossing the border at Namanga (tonnes/years) | 104,000 | 131,000 | - | Positive** |
To enhance tourism | N, of tourists crossing the borders | - | - | - | Positive** | |
To boost socio economic development | N, of new businesses along the road | - | - | - | Positive** |