| Expected | Actual |
Duration of procurement | Tanzania: 5 months | Tanzania: 18 months |
Kenya: 5 months | Kenya: 8 months | |
Duration of civil works* | Tanzania: 36 months | Tanzania: 42 months |
Kenya: 36 months | Kenya: 46 months | |
Cost | Tanzania: UA 40.3 million | Tanzania: N/A |
Kenya: UA 54.7 million | Kenya: UA 61.8 million |