| Expected | Actual |
| Duration of procurement | Tanzania: 5 months | Tanzania: 18 months |
| Kenya: 5 months | Kenya: 8 months | |
| Duration of civil works* | Tanzania: 36 months | Tanzania: 42 months |
| Kenya: 36 months | Kenya: 46 months | |
| Cost | Tanzania: UA 40.3 million | Tanzania: N/A |
| Kenya: UA 54.7 million | Kenya: UA 61.8 million |