| Task | Task Owner | Timeline |
| Project creation | Main Hospital | 3 months |
| Planning | Hospital | 4 months |
| Sensitizing Stakeholders | Director | 2 months |
| Authorities | Director | 2 weeks |
| Tender for construction of buildings | Procurement Department | 3 months |
| Bidder list | Procurement Department | 3 months |
| Assigning contract | Procurement Department | 3 weeks |
| Employee recruitment | HR | 2 months |
| Employee training | HR | 3 weeks |
| Job assignment | HR | 1 month |