Task

Task Owner

Timeline

Project creation

Main Hospital

3 months

Planning

Hospital

4 months

Sensitizing Stakeholders

Director

2 months

Authorities

Director

2 weeks

Tender for construction of buildings

Procurement Department

3 months

Bidder list

Procurement Department

3 months

Assigning contract

Procurement Department

3 weeks

Employee recruitment

HR

2 months

Employee training

HR

3 weeks

Job assignment

HR

1 month