Evaluation of success correctness or incorrectness of planning | Evaluation of success correctness or incorrectness based on the planned value and actual value of project that specifications change did not occur during development | ||||||||
121_ Planning of Quality | 122_Planning of Delivery | 120_Planning of Cost | Judge | 124_Actual result of Quality | Judge | 125_Actual result of Delivery | Judge | 123_Actual result of Cost | Judge |
x = 1.0: Target of Quality is clear and feasibility has been examined. | y = 1.0: Grounds of delivery time is clear and feasibility has been examined. | z = 1.0: Grounds of cost is clear and feasibility has been examined. | R | x = 1.2: Fewer than planned value more than 20% (0 ≤ x ≤ 80) | E | y = 1.2: Earlier than delivery time. (y < Planned Delivery time) | E | z = 1.2: Accomplished with cost that is lower than 20% of planned value. (0 ≤ z ≤ 90) | E |
x = 1.0: Fewer than planned value. (80 < x ≤ 100) | R | y = 1.0:According to Delivery time (y = Planned Delivery time) | R | z = 1.0: According to planned value. (Less than ±10%) (90 < z < 110) | R | ||||
x = 0.8: Excess within 50% of planned value. (100 < x ≤ 150) | W | y = 0.8: Less than 10 days late on Delivery time. (Planned Delivery time < y < Planned Delivery time +10) | W | z = 0.8: Excess within 30% of planed value. (110 ≤ z ≤ 130) | W | ||||
x = 0.6: Excess within 100% of planned value. (150 < x ≤ 200) | y = 0.6: Less than 30 days late on Delivery time. (Planned Delivery time +10 ≤ y< Planned Delivery time +30) | z = 0.6: Excess within 50% of planned value. (130 | |||||||
x = 0.2: Excess more than 100% of planned value. (200 < x) | y = 0.2: More than 30 days late on Delivery time. (Planned Delivery time +30 ≤ y) | z = 0.2: Excess more than 50% of planned value. (150 < z) | |||||||
x = 0.0: Quality target is not clear or feasibility is not examined. | y = 0.0: Grounds of the time of delivery plan are not clear and feasibility is not examined. | z = 0.0: Grounds of the cost calculation are not clear or feasibility is not examined. | W | --------- | I | --------- | I | --------- | I |
x, y or z = 0.0: No planning | I | I | I |