| Failure Mode |
Effect |
Safeguards |
Criticality |
| Fail to close on demand (FTC) |
Totally loss of primary barrier, increase the well leak probability. |
Periodic function test of DHSV. |
High |
| Leakage in closed position (LCP) |
If the leakage in within criteria, no significant consequence, otherwise the barrier element is considered degraded or failed. |
Periodic pressure test of DHSV. |
Medium |
| Premature valve closure (PCL) |
Lead to well shut-in unplanned, loss of production. |
|
Low |
| Fail to open on command (FTO) |
Loss of production. |
|
Low |
| Control line to well communication (CLW) |
Loss of hydraulic pressure leading to DHSV closed. Loss of production. |
|
Low |
| Well to control line communication (WCL) |
Since the pressure in the A annulus is higher than the control line, therefore the DHSV will fail to close in case of WCL. |
Periodic pressure test of control lines. |
High |