Factors | Number of Items | α | Variables | α1 |
Design Related | 5 | 0.47 | Insufficient and ambiguous information in drawings and specifications. | 0.36 |
Delayed delivery of drawings/designs. | 0.40 | |||
Rework caused by design changes or variation orders. | 0.55 | |||
The designer carried out inadequate research and analysis in the design phase. | 0.36 | |||
Insufficient exchange of information between the owner and designer in the design phase. | 0.40 | |||
Consultant Related | 6 | 0.82 | Delayed approval of contractor submissions by the consultant. | 0.79 |
Inadequate qualifications of the engineer’s staff assigned to the project. | 0.79 | |||
Delayed response from the consultant to contractor inquiries. | 0.86 | |||
Poor coordination by the consultant with other project stakeholders. | 0.75 | |||
Delays in inspection, performance, and testing by the consultant. | 0.77 | |||
Delays in rectifying errors in the contract document. | 0.78 | |||
Client Related | 5 | 0.44 | Client’s delays in making progress payments. | 0.38 |
Owner’s delays in providing and delivering the site to the contractor. | 0.47 | |||
Owner’s slow decision-making process. | 0.36 | |||
Client’s limitation of site supervisor’s authority. | 0.28 | |||
Excessive administrative bureaucracy within the owner’s organization. | 0.40 | |||
Contractor Related | 9 | 0.73 | Inefficient project scheduling and planning. | 0.71 |
Ineffective quality control. | 0.70 | |||
Improper implementation of construction techniques. | 0.71 | |||
Delays in mobilizing resources to the construction site. | 0.75 | |||
Inadequate contractor experience. | 0.70 | |||
Lack of contractor motivation to achieve early project completion. | 0.71 | |||
An insufficient technical study during the bidding stage. | 0.68 | |||
Inadequate communication with other project stakeholders. | 0.70 | |||
Frequent subcontractor changes due to their inefficient work and inadequate screening processes. | 0.70 | |||
Labor Related | 5 | 0.77 | Inadequate labor productivity. | 0.78 |
Shortage of manpower. | 0.71 | |||
Lack of skilled labor. | 0.72 | |||
Workforce strikes by the contractor. | 0.72 | |||
Low qualifications of the contractor’s technical personnel assigned to the project. | 0.73 | |||
External Factors | 7 | 0.69 | Modifications in government regulations, political interference. | 0.62 |
Impacts of underground conditions. | 0.71 | |||
Delays in obtaining permits from various government offices. | 0.66 | |||
Adverse weather conditions at the construction site. | 0.65 | |||
Unforeseen circumstances. | 0.63 | |||
Influence of cultural and social factors. | 0.61 | |||
Government procurement system favoring the lowest bidder. | 0.68 | |||
Material Related | 5 | 0.80 | Delays in material delivery and late ordering. | 0.77 |
Lack of skilled labor. | 0.72 | |||
Inadequate labor productivity. | 0.78 | |||
Workforce strikes by the contractor. | 0.72 | |||
Low qualifications of the contractor’s technical personnel assigned to the project. | 0.73 |