| Factors | Number of Items | α | Variables | α1 |
| Design Related | 5 | 0.47 | Insufficient and ambiguous information in drawings and specifications. | 0.36 |
| Delayed delivery of drawings/designs. | 0.40 | |||
| Rework caused by design changes or variation orders. | 0.55 | |||
| The designer carried out inadequate research and analysis in the design phase. | 0.36 | |||
| Insufficient exchange of information between the owner and designer in the design phase. | 0.40 | |||
| Consultant Related | 6 | 0.82 | Delayed approval of contractor submissions by the consultant. | 0.79 |
| Inadequate qualifications of the engineer’s staff assigned to the project. | 0.79 | |||
| Delayed response from the consultant to contractor inquiries. | 0.86 | |||
| Poor coordination by the consultant with other project stakeholders. | 0.75 | |||
| Delays in inspection, performance, and testing by the consultant. | 0.77 | |||
| Delays in rectifying errors in the contract document. | 0.78 | |||
| Client Related | 5 | 0.44 | Client’s delays in making progress payments. | 0.38 |
| Owner’s delays in providing and delivering the site to the contractor. | 0.47 | |||
| Owner’s slow decision-making process. | 0.36 | |||
| Client’s limitation of site supervisor’s authority. | 0.28 | |||
| Excessive administrative bureaucracy within the owner’s organization. | 0.40 | |||
| Contractor Related | 9 | 0.73 | Inefficient project scheduling and planning. | 0.71 |
| Ineffective quality control. | 0.70 | |||
| Improper implementation of construction techniques. | 0.71 | |||
| Delays in mobilizing resources to the construction site. | 0.75 | |||
| Inadequate contractor experience. | 0.70 | |||
| Lack of contractor motivation to achieve early project completion. | 0.71 | |||
| An insufficient technical study during the bidding stage. | 0.68 | |||
| Inadequate communication with other project stakeholders. | 0.70 | |||
| Frequent subcontractor changes due to their inefficient work and inadequate screening processes. | 0.70 | |||
| Labor Related | 5 | 0.77 | Inadequate labor productivity. | 0.78 |
| Shortage of manpower. | 0.71 | |||
| Lack of skilled labor. | 0.72 | |||
| Workforce strikes by the contractor. | 0.72 | |||
| Low qualifications of the contractor’s technical personnel assigned to the project. | 0.73 | |||
| External Factors | 7 | 0.69 | Modifications in government regulations, political interference. | 0.62 |
| Impacts of underground conditions. | 0.71 | |||
| Delays in obtaining permits from various government offices. | 0.66 | |||
| Adverse weather conditions at the construction site. | 0.65 | |||
| Unforeseen circumstances. | 0.63 | |||
| Influence of cultural and social factors. | 0.61 | |||
| Government procurement system favoring the lowest bidder. | 0.68 | |||
| Material Related | 5 | 0.80 | Delays in material delivery and late ordering. | 0.77 |
| Lack of skilled labor. | 0.72 | |||
| Inadequate labor productivity. | 0.78 | |||
| Workforce strikes by the contractor. | 0.72 | |||
| Low qualifications of the contractor’s technical personnel assigned to the project. | 0.73 |