Total Project Costs, considering different projections

Yearly Cost Breakout for Low Cost to Closure (10th percentile)

Item

Basis

Description

Duration

Sum (R$)

1

Prescribed action on chronogram

Contingency surface water/sediments sampling

13 years

949,000

2

Prescribed action on chronogram

Performance Based Action for Free Product

2 years

1,611,000

3

Contingency

Risk of continuation of Free Phase Action

2 additional years

588,000

4

Prescribed action on chronogram

One round of remediation

2 years

1,750,000

5

Likely required and based on 2017/18 monitoring results

Near term monitoring for performance confirmation

2 years

410,000

6

Contingency

Multilevel investigation

did not occur

0

7

Contingency

Additional rounds of remediation

2 years

1,270,000

8

Likely requirement once prescribed actions complete

Long-Term Monitoring Program

11 years

1,565,000

9

Likely requirement once prescribed actions complete

Report on delineation and use restrictions for obtaining Terms of Rehabilitation

1 event

250,000

Total

8,393,000

Yearly Cost Breakout for Median Cost to Closure (50th percentile)

Item

Basis

Description

Duration

Sum (R$)

1

Prescribed action on chronogram

Contingency surface water/sediments sampling

11 years

759,000

2

Prescribed action on chronogram

Performance Based Action for Free Product

2 years

1,603,000

3

Contingency

Risk of continuation of Free Phase Action

2 additional years

533,000

4

Prescribed action on chronogram

One round of remediation

2 years

2,370,000

5

Likely required and based on 2017/18 monitoring results

Near term monitoring for performance confirmation

2 years

460,000

6

Contingency

Multilevel investigation

5 years

839,000

7

Contingency

Additional rounds of remediation

2 years

2,370,000

8

Likely requirement once prescribed actions complete

Long-Term Monitoring Program

8 years

1,159,000

9

Likely requirement once prescribed actions complete

Report on delineation and use restrictions for obtaining Terms of Rehabilitation

1 event

275,000

Total

10,368,000

Yearly Cost Breakout for High Cost to Closure (90th percentile)

Item

Basis

Description

Duration

Sum (R$)

1

Prescribed action on chronogram

Contingency surface water/sediments sampling

15 years

990,000

2

Prescribed action on chronogram

Performance Based Action for Free Product

2 years

2,172,000

3

Contingency

Risk of continuation of Free Phase Action

3 additional years

807,000

4

Prescribed action on chronogram

One round of remediation

2 years

3,268,000

5

Likely required and based on 2017/18 monitoring results

Near term monitoring for performance confirmation

2 years

664,000

6

Contingency

Multilevel investigation

4 years

1,039,000

7

Contingency

Additional rounds of remediation

2 years

3,268,000

8

Likely requirement once prescribed actions complete

Long-Term Monitoring Program

13 years

1,237,000

9

Likely requirement once prescribed actions complete

Report on delineation and use restrictions for obtaining Terms of Rehabilitation

1 event

253,000

Total

13,698,000