SN | Workshop transit items | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
1 | NLG torque link apex pin for MPI | 7 Oct 12 | 7 Oct 12 | 1 day | |||||||||||
2 | Perform magnetic practice inspection Of the elevator inboard and Outboard servo controls rod eye ends | 7 Oct 12 | 9 Oct 12 | 3 days | |||||||||||
3 | Portable halon fire extinguishers for weight check | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
3 | Remove lavatory A, E, D fire extinguisher bottle for weight check | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
4 | Fwd and Aft gallery drain valve for cleaning (if applicable) | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
5 | Fwd cabin vacuum toilet rinse valve for cleaning | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
6 | Functional check Of pressure reducer for cargo fire extinguisher system | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
7 | Eng #1; clean integrated drive generator (IDG) Oil cooler | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
8 | Avionics—cleaning of Oxygen masks | 7 Oct 12 | 11 Oct 12 | 5 days | |||||||||||
SN | Major modifications | 6 Oct 12 | 12 Oct 12 | 7 days | |||||||||||
1 | Mod intro bearing assy On retract jack SB A320-57-1157 V00 R00 | 6 Oct 12 | 9 Oct 12 | 4 days | |||||||||||
2 | Avionics—Mod inst wiring prov for ATC/XPDR | 6 Oct 12 | 12 Oct 12 | 7 days | |||||||||||
3 | Avionics—Mod install RS422 wiring | 6 Oct 12 | 13 Oct 12 | 7 days | |||||||||||
4 | Avionics—Mod inst FDIMU from teledyn | 6 Oct 12 | 14 Oct 12 | 7 days | |||||||||||
5 | Avionics—Mod intro wiring provision for FDIU/DMU | 6 Oct 12 | 15 Oct 12 | 7 days | |||||||||||
6 | Avionics—Mod-wire harness inst at interface section 19/19.1 | 6 Oct 12 | 16 Oct 12 | 7 days | |||||||||||
7 | Wing: Install trunnion sliding panel with new attachment IAW SB A320-57-1147 Rev 03 | 7 Oct 12 | 9 Oct 12 | 3 days | |||||||||||
8 | Eng #1, Eng #2; O/w mod rpl deploy tube adaptor “o” ring | 7 Oct 12 | 9 Oct 12 | 3 days | |||||||||||
9 | Mod cockpit door module improvement | 8 Oct 12 | 8 Oct 12 | 1 day | |||||||||||
SN | Major restoration | 10 Oct 12 | 13 Oct 12 | 4 days | |||||||||||
1 | All required access panels and fairings | 10 Oct 12 | 13 Oct 12 | 4 days | |||||||||||
2 | All fuel tank access panels | 10 Oct 12 | 13 Oct 12 | 4 days | |||||||||||
3 | Electrical power On | 13 Oct 12 | 13 Oct 12 | 1 day | |||||||||||
SN | Functional checks | 13 Oct 12 | 14 Oct 12 | 2 days | |||||||||||
1 | System functionals | 13 Oct 12 | 14 Oct 12 | 2 days | |||||||||||
2 | LDG retraction test | 14 Oct 12 | 14 Oct 12 | 1 day | |||||||||||
SN | Final checks | 14 Oct 12 | 15 Oct 12 | 2 days | |||||||||||
1 | Refuel/leak check | 15 Oct 12 | 15 Oct 1 2 | 1 day | |||||||||||
2 | Eng wash+ Eng run | 15 Oct 12 | 15 Oct 12 | 1 day | |||||||||||
3 | Aircraft handover | 15 Oct 12 | 15 Oct 12 | 1 day | |||||||||||
5 Oct 12 | 6 Oct 12 | 7 Oct 12 | 8 Oct 12 | 9 Oct 12 | 10 Oct 12 | 11 Oct 12 | 12 Oct 12 | 13 Oct 12 | 14 Oct 12 | 15 Oct 12 | |||||
day 1 | day 2 | day 3 | day 4 | day 5 | day 6 | day 7 | day 8 | day 9 | day 10 | day 11 |