Project name | State | Technology | MGC (MW) | ICC ($Amil) | Cost ($A)/MWh | Reference |
Rewaste Plant at Yarra Valley Water | VIC | AD | 1 | 27 | 56 - 267 | Carlu, Truong [20] , Thi, Lin [32] |
Annual total output (MW) | Annual production cost (AUD) | Annual revenue (AUD) | Annual profit/loss (AUD) | Payback period (years) | ||
7425 | 415,800 to 1,982,475 | 623,700 | 207,900/1,358,775 | 130 | ||
Molong Solar Farm | NSW | Solar | 25 | 29 | 44.50 - 61.50 | Clean Energy Council [33] , ARENA [34] |
Annual total output (MW) | Annual production cost (AUD) | Annual revenue (AUD) | Annual profit/loss (AUD) | Payback period (years) | ||
45,864 | 2,040,948 to 2,820,636 | 3,626,256 | 1,582,308 to 805,620/NIL | 18 to 35 | ||
Ferguson Wind Farm | VIC | Wind | 12.6 | 26.5 | 50 - 65 | Clean Energy Council [33] , ARENA [35] |
Annual total output (MW) | Annual production cost (AUD) | Annual revenue (AUD) | Annual profit/loss (AUD) | Payback period (years) | ||
44,029 | 2,201,450 to 2,861,885 | 3,698,436 | 1,496,986 to 836,551/NIL | 18 to 32 |