Administrative Policies to Reduce the Negative Impact of Variation Orders

Mean

RII

Rank

AVO1

Audit planning is required by all involve parties before works start on site.

4.6273

0.9255

1

AVO9

Ensure that the drawings conform to the required specifications.

4.6087

0.9217

2

AVO10

The owner must be informed of the designs before bidding.

4.6025

0.9205

3

AVO5

Checking the specifications required in the contract.

4.5963

0.9193

4

AVO6

Effective communication between all parties concerned during the entire stages of the project.

4.5652

0.9130

5

AVO3

Carry out details site investigation including detail soil investigation during tendering stage.

4.5280

0.9056

6

AVO4

Commitment to the percentages specified in the contract for the value of the variable orders.

4.4907

0.8981

7

AVO2

Providing the project site with infrastructure services.

4.4348

0.8870

8

AVO8

Prepare the contract document before tendering stage.

4.4224

0.8845

9

AVO7

Forecast unforeseen situations before tendering.

4.4099

0.8820

10