Code | Administrative Policies to Reduce the Negative Impact of Variation Orders | Mean | RII | Rank |
AVO1 | Audit planning is required by all involve parties before works start on site. | 4.6273 | 0.9255 | 1 |
AVO9 | Ensure that the drawings conform to the required specifications. | 4.6087 | 0.9217 | 2 |
AVO10 | The owner must be informed of the designs before bidding. | 4.6025 | 0.9205 | 3 |
AVO5 | Checking the specifications required in the contract. | 4.5963 | 0.9193 | 4 |
AVO6 | Effective communication between all parties concerned during the entire stages of the project. | 4.5652 | 0.9130 | 5 |
AVO3 | Carry out details site investigation including detail soil investigation during tendering stage. | 4.5280 | 0.9056 | 6 |
AVO4 | Commitment to the percentages specified in the contract for the value of the variable orders. | 4.4907 | 0.8981 | 7 |
AVO2 | Providing the project site with infrastructure services. | 4.4348 | 0.8870 | 8 |
AVO8 | Prepare the contract document before tendering stage. | 4.4224 | 0.8845 | 9 |
AVO7 | Forecast unforeseen situations before tendering. | 4.4099 | 0.8820 | 10 |