| ECOs | Status | Remarks |
| Replace non-LED equivalent LED lights. | Implemented | Savings of 88,993 kWh/annum achieved |
| Install Vacancy Sensors to operate the rarely occupied sections | Implemented | Savings of 4040 kWh/annum achieved |
| Receptacles: install power strip to shut down plug loads | Pending | Estimated savings of 876 kWh/annum |
| VRV Upgrade of AC outdoor units | Ongoing | Estimated savings of 164,182 kWh/annum |
| Replace inefficient Split unit ACs with efficient ones | Ongoing | Estimated savings of 55,836 kWh/annum |
| Install Timers on Fan Motors for the extract fans | Implemented | Savings achieved 248,083 kWh/annum |
| Install the VSD controller for the compressor. | Pending | Estimated 78,840 kWh/annum |
| Install and implement Energy Management System | Pending | Estimated savings 111,103 kWh |
| Install Solar Water Heating Systems | Implemented | Savings 31,849 kWh/annum |