Equipment Type | # of Units | Total Module Cost ($000) |
Process Vessels | 3 | 790 |
Heat Exchangers | 2 | 10,000 |
Pumps | 20 | 12,000 |
Turbines | 3 | 360,000 |
Generators | 3 | - |
Total Bare Module Cost Contingency and Fees |
0.18*TBMC | 380,000 68,000 |
Total Module Cost Auxiliary Facilities |
0.1*TMC | 450,000 45,000 |
Fixed Capital Investment Working Capital |
0.05*FCI | 500,000 25,000 |
Total Capital Investment |
| 530,000 |