Processing math: 100%

Components

Exergoeconomic Parameters

cp

[$/GJ]

cf

[$/GJ]

˙CD

[$/hr]

˙ZJ

[$/hr]

˙ZJ+˙CD,J

[$/hr]

f

[%]

HP Turbine

9.979

3.319

0.07441

14.940

15.010

99.50

LP Turbine

9.979

5.205

0.26730

22.250

22.520

98.81

Condenser

2.386

2.319

0.32640

7.139

7.465

95.63

LP Pump 1

5.389

5.254

0.03096

4.003

4.034

99.23

Preheater 1

4.229

4.072

0.18450

6.831

7.016

97.37

LP Evaporator

3.135

2.912

0.12020

6.024

6.144

98.04

HP Pump 2

4.517

4.305

0.02919

6.349

6.378

99.54

Preheater 2

3.850

3.672

0.11000

7.208

7.318

98.50

HP Evaporator

3.263

3.118

0.16440

8.240

8.404

98.04

Superheater

3.319

3.251

0.00534

3.968

3.968

99.87