| Processes | Seke | Goromonzi | ||
| Achieved | Target | Achieved | Target | |
| Training of Personnel | 12 | 15 | 12 | 15 |
| Review and Planning meetings | 4 | 3 | 4 | 3 |
| Adverse events review meetings | 1 | 4 | 1 | 4 |
| Mobilisations | 12 | Monthly | 6 | Monthly |
| Support for outreach | Given 3 more nurses |
| Not given |
|
| Cost reimbursement | Delayed | Monthly | Delayed | Monthly |