| Case 1 w1 = 0.7, w2 = 0.3 | |||
Cost | Overall Reliability | Monthly Average Reliability | No. of Activities | |
SA | 20,043,091.06 | 51.62% | 98.18% | R = 44, M = 38 |
GA | 12,623,229.98 | 50.3 % | 98.11% | R = 35, M = 2 |
BPSO | 12,579,732.45 | 52.03% | 98.2% | R = 38, M = 1 |
| Case 2 RRreq = 0.5 | |||
Cost | Overall Reliability | Monthly Average Reliability | No. of Activities | |
SA | 17,787,577.04 | 51.62% | 98.18% | R = 44, M = 24 |
GA | 12,834,562.76 | 50.3% | 98.11% | R = 37, M = 2 |
BPSO | 12,510,299.90 | 51.94% | 98.2% | R = 38, M = 0 |