Activity | Normal Time (weeks) | Crash Time (weeks) | Crashed Time (weeks) | Normal cost ( | Crash cost ( | Crashed cost ( | Average Crashed cost ( |
A | 10 | 8 | 2 | 30 | 40 | 10 | 5 |
B | 8 | 6 | 2 | 120 | 150 | 30 | 15 |
C | 10 | 8 | 2 | 100 | 160 | 60 | 30 |
D | 7 | 6 | 1 | 40 | 50 | 10 | 10 |
E | 11 | 9 | 2 | 50 | 75 | 25 | 12.5 |
F | 3 | 3 | - | 60 | - | - | - |
G | 6 | 5 | 1 | 100 | 140 | 40 | 40 |
H | 3 | 1 | 2 | 30 | 40 | 10 | 5 |
I | 9 | 6 | 3 | 150 | 270 | 120 | 40 |
J | 5 | 3 | 2 | 180 | 190 | 10 | 5 |