N

Name

Enumeration of building objects

1

Financing fraction

for each object

0.05

0.125

0.175

0.25

0.08

0.12

0.13

0.07

2

Object complicacy

0.150

0.26

0.364

0.347

0.202

0.254

0.265

0.186

3

Percentage of works

fulfillment at objects,

28%

37%

42%

63%

17%

86%

91%

12%

4

Fraction of fulfilled

works,

0.014

0.046

0.0735

0.1575

0.036

0.1032

0.1183

0.0084

5

Residual works

at the objects

0.036

0.079

0.1015

0.0925

0.044

0.0168

0.0117

0.0616

6

Residual complicacy

of works

0.120

0.2

0.232

0.22

0.1374

0.0686

0.052

0.171

7

Relative residual

complicacy

0.8

0.77

0.64

0.63

0.68

0.27

0.2

0.92

8

Efficiency of works

fulfillment at objects

20%

23%

36%

37%

32%

73%

80%

8%