| Name of the contract |
Road |
General works (NRs) |
Maintenance works (NRs) |
Improvement works including additional works (NRs) |
Emergency works (NRs) |
Day works (NRs) |
Total contract amount (NRs) |
| RMDP/PBMC/ICB01 |
Chaurahawa-Phuljor |
13,635,818.2 |
1,464,709.091 |
59,288,453.96 |
1,114,821.82 |
604,090.909 |
76107894 |
| (% of total contract amount) |
17.92 |
1.92 |
77.90 |
1.46 |
0.79 |
100 |
|
| RMDP/PBMC/ICB02 |
Phuljor-Pathalaiya |
3,814,363.64 |
13,723,977.27 |
49,359,364.28 |
1,380,066.55 |
509,011.364 |
68,786,783.1 |
| (% of total contract amount) |
5.55 |
19.95 |
71.76 |
2.01 |
0.74 |
100 |
|
| RNDP/LCB/PBM1 |
Kohalpur-Bhurigaon |
3,688,000 |
2,938,000 |
37,518,600 |
2,961,700 |
640,950 |
47,747,250 |
| (% of total contract amount) |
7.72 |
6.15 |
78.58 |
6.20 |
1.34 |
100 |
|
| RNDP/LCB/PBM2 |
Bhurigaon-Lamki |
2,488,000 |
2,777,400 |
38,031,705 |
3,127,900 |
863,150 |
47,288,155 |
| (% of total contract amount) |
5.26 |
5.87 |
80.43 |
6.61 |
1.83 |
100 |
|
| RNDP/LCB/PBM3 |
Lamki-Attariya |
4,790,000 |
3,062,500 |
33,301,200 |
7,437,725 |
876,600 |
49,468,025 |
| (% of total contract amount) |
9.68 |
6.19 |
67.32 |
15.04 |
1.77 |
100 |
|
| RNDP/LCB/PBM4 |
Attariya-Gaddachowki |
3,650,000 |
3,688,500 |
39,561,900 |
2,350,375 |
730,850 |
49,981,625 |
| (% of total contract amount) |
7.30 |
7.38 |
79.15 |
4.70 |
1.46 |
100 |
|
| RNDP/ICB/HN |
Hetauda-Narayani |
7,445,050 |
1,096,524 |
119,192,235.4 |
7,157,353.5 |
5,038,906.95 |
139,930,070 |
| (% of total contract amount) |
5.32 |
0.78 |
85.18 |
5.11 |
3.60 |
100 |