Projects | Average of bidders’ Offer (INR)(A) | Project Cost (INR) (B) | Winner’s offer (INR) (C) | C/A (%) | C/B (%) |
Pr-1 | 578,955,819.50 | 600,000,000.00 | 541,718,515.00 | 93.6 | 90.29 |
Pr-2 | 560,045,576.00 | 652,018,837.12 | 537,524,143.00 | 96.0 | 82.44 |
Pr-3 | 148,558,236.00 | 151,311,616.51 | 136,120,676.00 | 91.6 | 89.96 |
Pr-4 | 401,717,221.75 | 435,735,213.47 | 372,420,036.00 | 92.7 | 85.47 |
Pr-5 | 694,344,982.00 | 729,457,990.25 | 617,731,977.00 | 89.0 | 84.68 |
Pr-6 | 552,977,822.33 | 595,512,890.96 | 545,262,748.00 | 98.6 | 91.56 |
Pr-7 | 319,475,425.00 | 340,769,907.69 | 309,755,259.00 | 97.0 | 90.90 |
Pr-8 | 605,285,964.20 | 623,598,090.96 | 546,964,937.00 | 90.4 | 87.71 |
Pr-9 | 537,451,403.80 | 578,633,246.35 | 502,877,507.00 | 93.6 | 86.91 |
Pr-10 | 579,256,642.25 | 698,333,424.59 | 453,990,619.00 | 78.4 | 65.01 |
Pr-11 | 9,864,289.75 | 10,574,375.56 | 7,478,718.00 | 75.8 | 70.72 |
Pr-12 | 18,989,253.50 | 22,574,375.56 | 18,817,893.00 | 99.1 | 83.36 |
Pr-13 | 3,374,055.75 | 5,566,789.37 | 2,938,827.00 | 87.1 | 52.79 |
Pr-14 | 8,276,067.00 | 9,000,000.00 | 5,382,798.00 | 65.0 | 59.81 |
Pr-15 | 88,474,895.67 | 90,000,000.00 | 73,470,443.00 | 83.0 | 81.63 |
Pr-16 | 22,211,877.25 | 25,000,000.00 | 18,938,435.00 | 85.3 | 75.75 |
Pr-17 | 51,589,099.00 | 52,000,000.00 | 41,732,546.00 | 80.9 | 80.25 |
Pr-18 | 65,087,310.20 | 69,000,000.00 | 54,024,082.00 | 83.0 | 78.30 |
Pr-19 | 33,185,996.00 | 35,000,000.00 | 32,183,445.00 | 97.0 | 91.95 |
Pr-20 | 16,047,961.00 | 19,000,000.00 | 15,047,356.00 | 93.8 | 79.20 |
Pr-21 | 11,689,464.95 | 14,000,000.00 | 10,588,564.95 | 90.6 | 75.63 |