Vehicles’ number in queue | 1 | 2 | 3 | 4 | 5 | 6 |
Approximate time Taprx(2) (in sec) spending of the given vehicle in the queue completely to approach to the “Yield” sign | 0 | 2.12 | 5.25 | 7.17 | 9.34 | 11.51 |
Average stopping timeTav.stp (in sec.) of the given vehicle before “Yield” sign | 15.23 | 28.41 | 42.33 | 57.22 | 71.24 | 83.11 |
The sum of these two time periods | 15.23 | 30.53 | 47.58 | 64.39 | 80.58 | 94.62 |
The delay dad.ln (in sec) of each vehicle due to the additional second lane of the roundabout can be found as | 35.72 | 48.36 | 63.46 | 79.20 | 92.96 | 103.83 |
Average delay dav (in sec) of these 6 vehicles or queue | 70.59 |