Checks

Yes/No

1) Sample Transfer Pressure within 0.15 to 0.25 MPa

2) Reactor operation check list followed prior to the start of reactor operation

3) Flux stable at the required flux (half power, 5 × 1011 n·cm−2·s−1 or full power, 1 × 1012 n·cm−2·s−1)

4) Coolant temperature rise within the range of (10˚C to 15˚C) for half power operation and (18˚C C to 25˚C) for full power operation

5) Reactor shutdown after operation (shutdown checks followed)