Factors affecting the performance of project consultants

N

RIA

RII (%)

Rank

1) Related to Management of Project

Adequate technical background

90

4700

52.22

20

Poor relationship among team members

90

2350

26.11

30

Ability to coordinate

90

5400

60.00

11

Ability to make decisions when necessary

90

6650

73.89

4

Competence of the team

90

4175

46.39

22

Ability to delegate authority

90

5300

58.89

14

Ability to work as a team

90

7575

84.17

1

2) Related to Cost Management

Accurate and reliable budget estimate

90

5775

64.17

7

Ability to foresee and budget for potential inflation

90

5150

57.22

15

Excessive variation orders

90

4025

44.72

23

Proper planning and scheduling of works

90

5625

62.50

9

Creativity in controlling their own cost and developing their efficiencies

90

7125

79.17

2

3) Related to Quality of Work

Design team experience

90

4975

55.28

17

Delay in producing design document

90

2550

28.33

29

Adequate material test records

90

5100

56.67

16

Excessive variation orders

90

2875

31.94

27

Excessive errors or omission

90

3325

36.90

26

4) Time Related

Coordination of contractors’ work promptly

90

6025

66.94

5

Timely decision making

90

5725

63.61

8

Timely submission of reports, payment certification, and claims

90

6975

77.50

3

Time for completing major specified work sections

90

3725

41.39

24

5) Environmental Related

Political influence from higher authority

90

5875

65.28

6

Economic influence in terms of remuneration and allowances

90

5575

61.94

10

Social in terms of family relations

90

2725

30.28

28

Weather influence

90

4825

53.61

19

Level of technological advancement

90

5375

59.72

12

6) Others

Project type

90

4525

50.28

21

Project value

90

5325

59.17

13

Project duration

90

4900

54.44

18

Urgency

90

3575

39.72

25