Software Evaluation criteria

MS-Project

Primavera P3

Operational characteristics

M = 60%

Range of Y (0 - 3)

Value of Y

Value of Y

1

Time management

2.01

2.28

2

Resource management

1.75

2.15

3

Cost management

1.59

2.12

4

Reporting

1.56

1.63

5

Control and monitoring

1.82

1.63

Value of A (operational)

Range (100 - 300)

178 points

209 points

General system characteristics

n ? 40%

1

Documentation

1.74

1.91

2

Compatibility

1.67

1.43

3

Security

1.35

1.91

4

Technical support

1.78

1.96

5

User friendliness

1.97

1.84

Value of B (general system)

Range (100 - 300)

179 points

181 points

Value of C (total weighted score)

Range (100 - 300)

178 points

198 points

Efficiency E %

59

66

Total cost AUS $/license

3100

13485

Cost effectiveness ratio CER

0.182

0.046