Year

Amount US$

Loan

Purpose

2000

$2,400,000.00

Concessional loan

Not Specified

2001

$3,600,000.00

Concessional loan

Not Specified

2002

$8,300,000.00

Concessional loan

Agriculture Equipment & Inputs

2003

$70,000,000.00

Concessional loan

Power Generation

2004

$1,000,000,000.00

Concessional loan

Kariba Hydro Power Station

2006

$200,000,000.00

Concessional loan

Agricultural Inputs

2007

$58,000,000.00

Concessional loan

Tobacco Farming

2008

$200,000,000.00

Concessional loan

Internal-Security

2009

$200,000,000.00

Export Buyers’ Credit

Not Specified

2010

$46,000,000.00

$30,000,000.00

Concessional loan

Concessional loan

Agricultural Inputs

Agriculture Machinery

2011

$342,000,000.00

Concessional loan

Medicine

2012

$162,000,000.00

$45,000,000.00

$51,000,000.00

Concessional loan

Concessional loan

Concessional loan

Victoria Fall Airport Telecommunication infrastructure

2013

$319,000,000.00

Concessional loan

Power Generation

2018

$1,000,000,000.00

$77,000,000.00

Concessional loan

Concessional loan

Hwange Power Station

Construction of a New Parliamentary Building

2019

$153,000,000.00

Concessional loan

Refurbishment of Robert Mugabe Airport