Constructions to be realised | Surface area covered | Number (N) | Unit cost (in FCFA) | Total cost (in FCFA) |
Construction of shops | 16.22 m2 | 200 | 2,012,300 | 402,460,000 |
Construction of type 1 hangars | 393.24 m2 | 5 | 27,653,820 | 138,269,100 |
Construction of type 2 hangars | 393.24 m2 | 2 | 25,930,755 | 51,861,510 |
Construction of open air counters | 205.2 m2 | 15 | 594,673.3 | 8,920,100 |
Construction of ground counters | 136.6 m2 | 10 | 575,240 | 5,752,400 |
Construction of the police post | 32.01 m2 | 1 | / | 26,527,423 |
Construction of cold store and warehouse | 152.34 m2 | 1 | / | |
Construction of public toilettes and water points | 36.60 m2 | 2 | 13,033,060 | 26,066,120 |
Construction of paid parking | 1999.04 m2 | 1 | 79,604.2 | 159,132,140 |
Construction of the motor park esplanade | 2553.49 m2 | 1 | 80,056.6 | 204,423,965 |
Building road pavements inside the market | 1925 m2 |
| 25,000 | 48,125,000 |
Reorganising the electrical network | / | 1 | 3,563,000 | 3,563,000 |
Building the general drainage system | 182.7 m2 | 1 | 15,000 | 2,740,500 |
Purchase of garbage cans | 7.5 m2 | 3 | 250,000 | 750,000 |
Financing environmental impact assessment | / | 1 | 2,000,000 | 2,000,000 |
Financing the technical studies | / | 1 | 4,500,000 | 4,500,000 |
Total cost of the project | 1,085,091,258 |