Constructions to be realised

Surface area covered

Number

(N)

Unit cost (in FCFA)

Total cost (in FCFA)

Construction of shops

16.22 m2

200

2,012,300

402,460,000

Construction of type 1 hangars

393.24 m2

5

27,653,820

138,269,100

Construction of type 2 hangars

393.24 m2

2

25,930,755

51,861,510

Construction of open air counters

205.2 m2

15

594,673.3

8,920,100

Construction of ground counters

136.6 m2

10

575,240

5,752,400

Construction of the police post

32.01 m2

1

/

26,527,423

Construction of cold store and warehouse

152.34 m2

1

/

Construction of public toilettes and water points

36.60 m2

2

13,033,060

26,066,120

Construction of paid parking

1999.04 m2

1

79,604.2

159,132,140

Construction of the motor park esplanade

2553.49 m2

1

80,056.6

204,423,965

Building road pavements inside the market

1925 m2

25,000

48,125,000

Reorganising the electrical network

/

1

3,563,000

3,563,000

Building the general drainage system

182.7 m2

1

15,000

2,740,500

Purchase of garbage cans

7.5 m2

3

250,000

750,000

Financing environmental impact assessment

/

1

2,000,000

2,000,000

Financing the technical studies

/

1

4,500,000

4,500,000

Total cost of the project

1,085,091,258