| SL | Question | Feedback | |
| Per % | Responses | ||
| 1 | Risk is lower in agile project compare to traditional project? | ||
| Strongly agree | 20% | 10 | |
| Agree | 43% | 21 | |
| Neutral | 4% | 2 | |
| Disagree | 22% | 11 | |
| Strongly disagree | 10% | 5 | |
| 49 | |||
| 2 | Split project to many waves (smaller pieces) reduces risk and fulfill quality requirement easily | ||
| Strongly agree | 22% | 11 | |
| Agree | 63% | 31 | |
| Neutral | 6% | 3 | |
| Disagree | 6% | 3 | |
| Strongly disagree | 2% | 1 | |
| 49 | |||
| 3 | Managing risks in agile project is different than traditional project | ||
| Strongly agree | 18% | 9 | |
| Agree | 63% | 31 | |
| Neutral | 16% | 8 | |
| Disagree | 0% | 0 | |
| Strongly disagree | 2% | 1 | |
| 49 | |||
| 4 | Adopting hybrid approach help to mitigate risks easier in agile project | ||
| Strongly agree | 12% | 6 | |
| Agree | 57% | 28 | |
| Neutral | 29% | 14 | |
| Disagree | 0% | 0 | |
| Strongly disagree | 2% | 1 | |
| 49 | |||
| 5 | Risk can be controlled in agile environment | ||
| Strongly agree | 14% | 7 | |
| Agree | 57% | 28 | |
| Neutral | 22% | 11 | |
| Disagree | 6% | 3 | |
| Strongly disagree | 0% | 0 | |
| 49 | |||
| 6 | Current risk practice in agile project is suiting the requirement | ||
| Strongly agree | 10% | 5 | |
| Agree | 45% | 22 | |
| Neutral | 35% | 17 | |
| Disagree | 10% | 5 | |
| Strongly disagree | 0% | 0 | |
| 49 | |||
| 7 | Agile risk depend on the maturity and the knowledge of practice area | ||
| Strongly agree | 27% | 13 | |
| Agree | 59% | 29 | |
| Neutral | 4% | 2 | |
| Disagree | 8% | 4 | |
| Strongly disagree | 2% | 1 | |
| 49 | |||
| 8 | We need to enhance risk management in agile project | ||
| Strongly agree | 27% | 13 | |
| Agree | 47% | 23 | |
| Neutral | 20% | 10 | |
| Disagree | 6% | 3 | |
| Strongly disagree | 0% | 0 | |
| 49 | |||
| 9 | Fast change in requirement in agile make risk out of control | ||
| Strongly agree | 6% | 3 | |
| Agree | 55% | 27 | |
| Neutral | 14% | 7 | |
| Disagree | 22% | 11 | |
| Strongly disagree | 2% | 1 | |
| 49 | |||
| 10 | Agile risk can be under control even with less documentation | ||
| Strongly agree | 6% | 3 | |
| Agree | 33% | 16 | |
| Neutral | 16% | 8 | |
| Disagree | 35% | 17 | |
| Strongly disagree | 10% | 5 | |
| 49 | |||